Production Run Mgt - Questions
This is a Planning and Development screen
Please review:
This is a Planning and Development screen
DO we set the start time for all the WO's in the header of the PR, or by WO and earliest or first start time sets the schedule for the whole Production Run.
Yes, a Roll over, or a carry forward; would be useful, BUT a KPP Zero and a QA First OFF must still be done.
If the Resin Lot changes; we the RUN goes to a Suspended Status (Maybe a Resin lot Change Status). Production Values on Production Parts are Totaled and closed off. THEN we continue, BUT are we continuing or Rolling Over???
WE could do an actual roll over, it closes the original run, carry every thing forward, including the KPP Zero and QA first off BUT give it a new PR ID. This might make it easier to the auto generate the new rows in the Daily Production Report.
Charlies Scheduling worksheet